Successful Collaborations in Nottinghamshire

Collaboration and Consistency is Pillar 5 of our Vision

Potentially setting a record, with 10 different projects being executed simultaneously during Cadent's planned Mains Replacement in Nottinghamshire. The team responsible for Streetworks at Nottinghamshire County Council are proud of this achievement.

  • Cadent (Planned Works Mains Replacement) - 29th July – 7th October – This was the Basic job that everything else collaborated with!
  • Cadent (New Connection into a dwelling on Main Street). – 12th August – 16th August
  • National Grid – (Electricity New Ducting & Cabling from Nine Corners into James Street) - 29th July – 6th September
  • Severn Trent Water – (Sewer repair junction Greens Lane) – 9th September.
  • Virgin Media – (Clear Blockage) - 30th – 31st July
  • Open Reach (Ducting works) 30th August – 2nd September
  • National Grid (Joint holes) 30th August – 10th September
  • Cadent (Remedial works for previous immediate works) - 28th August
  • VIA (patching works) - 28th August
  • National Grid (Reinforcement scheme) 12th August – 6th September