New guidance from the DfT - applies from the 5th January 2026
This code of practice provides practical guidance on the responsibilities of authorities and undertakers under the New Roads and Street Works Act (1991) (NRSWA).
It applies from 5 January 2026 and helps:
- local authorities to co-ordinate works in the highway under section 59 of NRSWA
- undertakers to fulfil their duty to co-operate in this process under section 60 of NRSWA
It reflects the Street and Road Work Charges and Penalties Regulations 2025, which:
- increased the level of fixed penalty notices for street works offences
- extended overrun charges to weekends and bank holidays where works extend beyond the agreed duration